Viewing inquiries for 10-1L3404
Submit new inquiry for this projectInquiry #1: 1. The roadway excavation and jointed plain concrete pavement don't seem to line up. How can you take 280CY more out then you put back?
2. Typically lean base concrete would be placed under the jointed plain concrete pavement, with the bond breaker between the sections. Are placing the bond breaker on the existing subgrade?
Inquiry submitted 06/30/2025
Response #1:bidder inquiry is in review
Response posted 06/30/2025
Response #2:addendum will be issued.
Response posted 07/03/2025
Inquiry #2: After reviewing plan page C-1 we some some issues. There does not seem to be a joint between lanes 1 & 2 (no tie bars).
1. Is it Caltrans intention to pour lanes 1&2 at the same time? If so, how do we accomplish this with lane closure chart G1 that specifies we must keep one lane open in each direction of travel?
In past WIM projects we pour one lane at a time and drill and bond in tie bars.
Inquiry submitted 06/30/2025
Response #1:bidder inquiry is in review
Response posted 06/30/2025
Response #2:addendum will be issued.
Response posted 07/03/2025
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.