Submit new inquiry for this projectInquiry #1: FYI-Caltrans to-All Bidders- How do I register for Mandatory Pre-Bid Meeting?
Inquiry submitted 05/12/2025
Response #1:Please do not use the Bidder Inquiry platform for Mandatory Pre-Bid Meeting registration; It is for inquiries related to bidding on the project contract. Register in advance of the Mandatory Pre-Bid Meeting, and no later than 1 hour before the meeting time, by sending an email with bidder information to D4.Construction.Duty.Senior@dot.ca.gov Please include the project number & "Mandatory Pre-Bid Meeting", within the subject of the email.
Response posted 05/12/2025
Response #2:Companies that attended the Mandatory Pre-Bid Meeting: • ACC West Coast & Ragnar Benson A Joint Venture • Alfaro Communications Construction,Inc. • American Civil Constructors West Coast LLC • Anvil Builders Inc • Bay Cities Paving & Grading, Inc. • Bridge Masters, Inc. • Cooper Energy Services • Crosstown Electrical & Data, Inc. • DMZ Builders • Fibertel CA, LLC • IENGCO • MARTIN BROTHERS CONSTRUCTION • Mastec North America • MP Nexlevel of California, Inc. • NET ELECTRIC, INC • Pavement Data Group, Inc. • PTM General Engineering Services Inc. • Purus Inc • RTS Management Solutions, Inc • Silicon Valley Consulting Group • St. Francis Electric, LLC. • Studebaker Electric, Inc • Teichert Energy & Utilites • TR Digital Inc •
Response posted 06/09/2025
Response #3:For the contact list, click on the link: http://website.dot.ca.gov/dist4/construction/contracts/04-155004/MPBM%20Contact%20List%2004-155004.pdf
Response posted 06/09/2025
Inquiry #2: Is it possible to release the digital files for these plan sets?
Inquiry submitted 05/19/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025
Response #2:The digital files are not provided.
Response posted 06/26/2025
Inquiry #3: Do the new bolts that connect the new MDCS Support Brackets to the Existing Steel Truss Bottom Chord Members utilize existing bolt holes in the Bottom Chord Members or are new bolt holes required in the Existing Steel Truss Bottom Chord Members.
Inquiry submitted 05/19/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025
Response #2:Please see Typical Details No. 1 on plan sheet 527 of 587, Typical Details No. 2 on plan sheet 528 of 587, and Typical Details No. 3 on plan sheet 529 of 587. Existing bolts are labelled “existing”. Please bid per the contract documents.
Response posted 05/22/2025
Inquiry #4: Please provide access details to the inside of the Existing Steel Truss Bottom Chord Members to allow connection of the new bolts for the MDCS Support Brackets within the Existing Steel Truss Bottom Chord Members (top and bottom sides of existing chords).
Inquiry submitted 05/19/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025
Response #2:Please refer to paragraph 9 in section 2-1.06B of the standard specifications and the “Supplemental Project Information” table in section 2-1.06B of the special provisions. Bid per the current contract documents.
Response posted 06/26/2025
Inquiry #5: Please provide existing paint preparation and/or abatement requirements at the new MDCS Support Bracket locations
Inquiry submitted 05/19/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025
Response #2:Please refer to section 14-11.13 of the special provisions for specifications about disturbing existing paint systems
Response posted 05/22/2025
Inquiry #6: Please provide paint requirements on the faying surface between the new MDCS Support Brackets and the Existing Steel Truss Bottom Chord Members.
Inquiry submitted 05/19/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025
Response #2:Please refer to section 14-11.13 of the special provisions for specifications about disturbing existing paint systems.
Response posted 06/24/2025
Inquiry #7: Is the Contractor allowed to use the existing Caltrans Access Travelers on both Carquinez Bridges?
Inquiry submitted 05/19/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/19/2025
Inquiry #8: There seems to be discrepancies between the quantities show on the Table beginning on Sheet C-1 and the line-work in the Modifying Existing Electrical Systems Layout sheets. For example; the table on C-1 indicates that Sheet E-3 has 810 LF of "Four 2-inch Fiber Optic Conduit (Trench in Pavement Method Travel Lane)" however, the notes indicated on sheet E-3 make no such reference and seem to indicate that there is only 50 LF of 3" new conduit is to be placed on that sheet. Can you please clarify?
Inquiry submitted 05/21/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/21/2025
Inquiry #9: Conduit Installation Details:
There are numerous locations of conduits shown on Drawings E-3 thru E-115 that reference the Project Notes on Drawings E-1 and E-2. Several Project Notes do not provide installation details of the conduit. I.e., is the conduit existing, is it to be installed in a new trench, is it to be directional drilled. Please provide installation details for the following Project Note Numbers: 2,21,22,23,24,39,40,57,58,75 shown on Drawings E-1 and E-2.
For example, Drawing E-61 shows conduits referencing Project Notes 2,21,23,24. These notes do not provide any conduit installation details.
Inquiry submitted 05/21/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/21/2025
Response #2:Wherever installation method is not specified, the default is trenching as per standard plans.
Response posted 06/03/2025
Inquiry #10: For Bid Item 11 MOBILE BARRIER SYSTEM, please clarify if the Daily Rate is for one system or all systems used each day.
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Response #2:The daily rate is for all systems used each day.
Response posted 06/26/2025
Inquiry #11: For Bid Item 12 MOBILE BARRIER TRAILER, please clarify if the Monthly Rate is for one MBT or all MBT's used each month.
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Response #2:The monthly rate is for all trailers each month.
Response posted 06/26/2025
Inquiry #12: For Bid Item 8 STATIONARY IMPACT ATTENUATOR VEHICLE, please clarify if the Daily Rate is for one vehicle or all vehicles used each day.
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Response #2:Please refer to Section 12-3.23 on the Standard Specifications. The daily rate is for all vehicles used each day.
Response posted 06/26/2025
Inquiry #13: Structure Plan Sheet 474 (80/580 EL CERRITO SEPERATION OH) shows the new MDCS attached to the bridge structure. Plans E-27 and E-28 show the same conduits as Type 77 and 74 (Trench and Directional Drill). Please clarity what method of installation is required at this location.
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Inquiry #14: Given the highly variable nature of the existing pavement sections, it follows that the difficulty of trenching, potholing, and any other required excavation in pavement will also vary greatly. Can you please provide existing pavement sectional details?
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Inquiry #15: Specification Section 12-3.24 MOBILE BARRIER SYSTEMS requires the use of Mobile Barrier Systems for most of the work on this project. Using Caltrans Mobile Barrier System Guidelines (dated December 2023), the estimated cost of one Mobile Barrier System is $2,000 per day. Per Section 12-3.24B, the rental cost for one Mobile Barrier Trailer is $25,000 per month. Additionally, the use of MBT’s will significantly impact production while installing the Multi Duct Conduit System trenches along the Caltrans ROW. These requirements will add substantial costs to the project. Please consider allowing the use of more typical Caltrans lane closures for this project (in particular for the new MDCS trenches).
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Inquiry #16: Due to the high variability of paving section thickness and composition throughout the project area and the subsequent variable effect that it will have on all excavation activates, can you please release information on the existing paving sections?
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Inquiry #17: On sheets E-3 to E-115 there are many contradicting instances where the lines and notes indicate a new length of conduit merging into an existing conduit with no notes indicating a continuation of the new conduit along the existing conduits or a method of installation were new conduits to be placed. Additionally, the provided Quantities tables contradict what is shown in the layouts.
For example: on E-9, near EB1 Line 174+75, there is a length of 137' of Note 77 (new 4-1.5" C) sweeping away from a run of notes 6 (Existing conduits, pull FO cables) & 78 (Existing, for reference only). The notes seem to imply that the 137' of note 77 is installed without continuing along with notes 6 & 78. Please clarify and/or correct what exact materials and methods are to be used.
Inquiry submitted 05/22/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/22/2025
Inquiry #18: Sheet 323 (E-34) shows conduits crossing Carlson Blvd at two locations. Please provide details of conduit installation at both crossings. I.e. trench or directional drill
Inquiry submitted 05/23/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025
Inquiry #19: The Mobile Barrier System that Caltrans is requiring is adding significant cost to this project and in the contractors view is unnecessary. Please consider removing this item and instead allowing standard lane closures in its place.
Inquiry submitted 05/23/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025
Response #2:There are no plans to remove the Mobile Barrier System at this time. Please bid per current contract documents.
Response posted 05/28/2025
Inquiry #20: Sheet 374 (E-85) shows a conduit run from Route 80 EB viaduct down to an existing cabinet (TV972) located adjacent to Dowrelio Drive at ground level. Please provide details of the conduit run down the viaduct column I.e. new conduit or existing conduit.
Inquiry submitted 05/23/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025
Response #2:Apply the industry standard conduit mounting practice to carry conduits to existing/new elements.
Response posted 06/24/2025
Inquiry #21: Addendum 2 replaced the thirteenth paragraph in the notice to bidders with a mandatory pre-bid on June 2, 2025. Do interested contractors need to request an updated Webex link from the link previously provided for May 29?
Inquiry submitted 05/23/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025
Response #2:When the Mandatory Pre-Bid Meeting date changes, the meeting link that the contractor receives when registering will also work for the new date.
Response posted 05/23/2025
Inquiry #22: Sheet 396 (E-107) shows new conduit being trenched across Route 980, please confirm this is a trench (Project Note 85) or should it be directional drill method?
Inquiry submitted 05/23/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/23/2025
Inquiry #23: Sheet 346 (E-57) shows new conduit installed with Directional Drilling Method under all EB Route 80, the median and about two lanes of WB Route 80, then continues across EB Route 80 with a detail described by Project Note No.58 on E-2. Please provide clear conduit routing details across Route 80 at Richmond Parkway.
Inquiry submitted 05/27/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025
Response #2:Bid for HDD for all lateral connections if the trunkline is on one side and element is on the other side of the freeway.
Response posted 06/26/2025
Inquiry #24: Sheet 354 (E-65) shows new conduit crossing Pinole Valley Rd (south side of Route 80). Please confirm that this conduit is actually installed per Project Note 77 shown on E-2 (I.e. trench across Pinole Valley Road).
Inquiry submitted 05/27/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025
Response #2:Yes. Note 77 is confirmed, install conduit across Pinole Valley Road.
Response posted 05/30/2025
Inquiry #25: Sheet 358 (E-69) shows new conduit installed in a trench crossing Sycamore Ave, a railroad and Willow Ave (per Project Note 77). Table on Sheet 17 (C-2) shows 790LF of conduit "Attached to Structures" on Sheet E-69. Please confirm that the new conduit in this location is actually attached to the bridge structure (not trench) and please also provide structural details of this.
Inquiry submitted 05/27/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025
Inquiry #26: Sheet 359 (E-70) shows new conduit installed in a trench crossing Route 4 (per Project Note 77). Table on Sheet 15 (C-2) shows 545LF of conduit "Attached to Structures" on Sheet E-70. Please confirm that the new conduit in this location is actually attached to the bridge structure (not trench) and please also provide structural details of this.
Inquiry submitted 05/27/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/27/2025
Inquiry #27: Sheet 373 (E-84) shows new conduit installed in a new trench across the EB lanes of Route 80. Is this correct or should these conduits be installed with directional drill method?
Inquiry submitted 05/28/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025
Response #2:Yes. It is correct. Installed via directional drilling method.
Response posted 06/24/2025
Inquiry #28: Due to the absence of sufficient bore logs to determine the presence of ground water, and the design of the trenching and horizontal directional drilling details provided, we are assuming there will not be ground water present. Please confirm this is correct.
Inquiry submitted 05/28/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025
Response #2:Please see the Geotechnical Report shown in the IH under Supplemental Info.
Response posted 06/24/2025
Inquiry #29: The geo technical reports have very few bore logs, can Caltrans please release additional bore logs for this project?
Inquiry submitted 05/28/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025
Response #2:Additional bore logs are not available. Please bid per current contract documents.
Response posted 06/24/2025
Inquiry #30: Sheet E-100 Calls out to Horizontal Directional Drill across 580 to a FVS110 on East Bound 580. There doesn't seem to be a Fiber vault in that area, is that are to be sawcut, jackhammer out to locate the existing conduit in the concrete overpass?
Inquiry submitted 05/28/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/28/2025
Response #2:FOVS will be attached to Structure. From this box 3" conduit will be routed along Peralta St, mounted to Structure. Factor in the cost for HDD from FOVS to TV104.
Response posted 06/26/2025
Inquiry #31: Notes 77 and 85 on Sheet E-2 describe (4) 1-1/2"C, see details on Sheet ED-23 and ED-55. Sheet ED-23 Type A detail shows a 4" steel conduit casing with (4) 1-1/4" innerducts inside of the 4" steel conduit. Is a 4" steel conduit required everywhere the Note 77 and 85 installations are shown or is PVC/HDPE conduit acceptable? Also, are we to install (4) 1-1/4" HDPE innerducts or (4) 1-1/2" HDPE innerducts inside of the 4" conduit?
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:4” steel conduit casing is required when you cross bridges/structure. Any where else when trench is the method to run conduits, bundle 1-1/2" conduits without casing.
Install (4) 1-1/4" HDPE innerducts inside of the 4" conduit casing.
Response posted 06/24/2025
Inquiry #32: Note 2 on Sheet E-1 describes a 3"C from splice vault to cabinet. Many of the Note 2 installations are associated with Note 74 on Sheet E-2, which states to install conduit by horizontal directional drilling method. Is steel conduit required for these installations or is PVC/HDPE acceptable?
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:PVC/HDPE is acceptable.
Response posted 06/24/2025
Inquiry #33: Multiple Notes on Sheets E-1 and E-2 describe ethernet cables. In many instances, the distances of the ethernet cable runs exceed the 300' threshold, which is the maximum distance that they will test out at. Is fiber optic cabling required in these instances where the distance exceeds 300'?
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:Yes.
Response posted 06/24/2025
Inquiry #34: Sheet E-4 shows existing fiber optic conduit runs, per notes 1, 78, 81, and 83. Sheet E-4 also shows what appears to be a new FOV and FSV003. Are the FOV and FSV003 new vaults? If so, please provide an installation detail showing how we are to intercept the existing fiber optic conduit runs (with existing innerducts and fiber optic cable installed inside the innerducts) and install the new FOV and FSV003. This is a typical installation that is shown on multiple plan sheets.
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:From E-2 TO E-14 along trunkline conduits and vaults will be in place. Run FO in existing conduits.
For lateral connection, both conduit and FO work is required.
Response posted 06/24/2025
Inquiry #35: Sheet E-10 shows an existing fiber optic conduit run, per Notes 6 and 78. Sheet E-10 also shows new fiber optic conduit runs, per Note 77. How do the new fiber optic conduit runs with (4) 1-1/2" innerducts (Note 77) tie into the existing fiber optic conduit runs with (4) 1-1/2" innerducts (Notes 6 and 78)? Please provide an installation detail.
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:From SFOBB bid for threading FO cables, no trench work for trunkline and no conduit work for trunkline but bid for lateral conduit and FO.
Response posted 06/24/2025
Inquiry #36: Notes 32, 76, 77, 85, and 88 all describe new conduit runs for the fiber optic trunk lines. These notes are shown on multiple plan sheets, but the dashed lines, which indicate the routing, do not appear to be very specific. For example, the dashed lines are shown at the edge of pavement, in lanes of traffic, in green space areas, under existing roads, crossing bridges, etc. Is it the contractors responsibility to determine the correct routing and installation methods for the fiber optic trunk line conduits or can more specific details be provided with more specific routing?
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:These notes refer to conduit run either along structure or on bridge. Contractor is provided correct routing method through plan sheets however where it leaves roadway and climb the structure transition vaults/boxes location may vary.
Response posted 06/24/2025
Inquiry #37: Sheet E-102 (Note 94) shows a new 4"C, containing (4) 1-1/4" innerduct, which is to be attached to the wall by using hangers/brackets/clamps. The routing of the Note 94 conduit on Sheet E-102 crosses 2 lanes of traffic, so this conduit is not able to be installed to the barrier wall. Please provide an installation detail or revised routing for the conduit.
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:Apply the industry standard conduit mounting practice to carry conduits to existing/new elements.
Response posted 06/24/2025
Inquiry #38: Please provide the Caltrans standard for Ethernet cabling slack required at handholes and cabinets.
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:Caltrans will accept the industry wide typical standard practices; Contractors should submit industry wide typical standard practices of ethernet cabling slack at handholes and cabinets for the RE's approval.
Response posted 06/26/2025
Inquiry #39: Sheet ED-23 shows a Trench in Dirt Detail, a Horizontal Boring Detail, and a Trench in Pavement Detail. The Trench in Pavement Detail references the Detail FC Type B Detail, which describes a 2" Type 3 (PVC) Schedule 80 conduit. Notes 77 and 85 on Sheet E-2 Describe (4) 1-1/2" conduits, but they also reference the Sheet ED-23 detail. Should the Trench in Pavement detail shown on ED-23 include a 4" conduit with (4) 1-1/2" innerducts or 2" Schedule 80 conduits?
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Response #2:Trench in pavement is bundle of 1 ½ “ conduits no casing. But on structure bundle 1 ¼ “ conduits inside 4” steel casing.
Response posted 06/24/2025
Inquiry #40: Bid Item Number 390132 Hot Mix Asphalt (Type A) includes a quantity of 850 Tons. Given that every Trench in Pavement conduit installation includes a 4' wide asphalt removal (and subsequent 4' wide hot mix asphalt patch), this quantity of 850 tons does not appear to be enough to cover the entire project. Is this quantity of 850 tons related to the patching associated with the Trench in Pavement conduit installation? Or is the 4' wide asphalt removal and 4' wide patching incidental to the Modifying Existing Electrical Systems pay item?
Inquiry submitted 05/29/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 05/29/2025
Inquiry #41: Please provide Mandatory sign-in sheet
Inquiry submitted 05/30/2025
Response #1:The Mandatory Pre-Bid Meeting sign in sheet will be available after it takes place on Monday, 6/2.
Response posted 05/30/2025
Inquiry #42: Please provide Freeway Lane Requirement Charts for Sheets 355-558 (E-66 to E-69) in EB direction.
Please provide Freeway Lane Requirement Charts for Carquinez Bridges Sheets 375-379 (E-86 to E-90) in EB and WB directions.
Inquiry submitted 05/30/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025
Inquiry #43: Please provide Freeway Lane Requirement Charts for Sheets 355-558 (E-66 to E-69) in EB direction.
Please provide Freeway Lane Requirement Charts for Carquinez Bridges Sheets 375-379 (E-86 to E-90) in EB and WB directions.
Inquiry submitted 05/30/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025
Inquiry #44: Please provide Freeway Lane Requirement Charts for Sheets 387 to 400 (E-98 to E-111) in both directions.
Inquiry submitted 05/30/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025
Inquiry #45: E-107 calls out 85 which refers you to a trench detail. Most of the area is a freeway overpass which no excavation can happen in that area. There is also a large building against the freeway overpass. Is a portion of that work to be on the overpass in a steel casing? It also shows the trench to be crossing multiple lanes on Route 980. Please verify with more accurate details for this area.
Inquiry submitted 06/02/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025
Inquiry #46: Sheet 328 (E-39) shows new trench (Project Note 77) running between the EB 80 and Home Depot Building and Parking Lot. Please confirm exact location of new trench as it seems like there is no space for it.
Inquiry submitted 06/02/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025
Inquiry #47: Sheet 106 calls out #85 which is trench detail #23, but there is also a structural detail on page 572 Multi Duct Conduit system 27th St. UC. Which are we to follow?
Inquiry submitted 06/02/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/02/2025
Response #2:Note # 85 is for trenching.
ED-23 provides the methods which will be applied whether conduit is run on dirt or on the structure.
Response posted 06/24/2025
Inquiry #48: Can we have the sign in from the job walk?
Inquiry submitted 06/03/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/04/2025
Response #2:Please see Bidder Inquiry No. 1 for the list.
Response posted 06/24/2025
Inquiry #49: Sheet 386 (E-97) shows the new conduit trench crossing Route 780. The trench location when crossing Rt 780 (as shown on E-97) is located within the concrete bridge structure. Please clarify.
Inquiry submitted 06/03/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/04/2025
Response #2:Crossing freeway 780 mount conduits to structure for route 80 EB.
Response posted 06/24/2025
Inquiry #50: Sheet 299 (E-10) shows new conduit run crossing Route 80/580 (Type 2). Please confirm this will be directional drill method of installation.
Inquiry submitted 06/03/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/04/2025
Response #2:Yes. HDD will be used.
Response posted 06/24/2025
Inquiry #51: Please provide a list of the Caltrans approved material suppliers for conduit materials as shown on detail sheet ED-1
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Response #2:Caltrans will review and make a decision for contractor supplied material.
Response posted 06/24/2025
Inquiry #52: An extensive estimating effort is needed for this project given it's overall length, the multiple types of underground raceway/trench sections, aboveground raceway/details for attaching to diverse concrete and steel structures, and providing traffic control for all the various work in a very complex urban transportation corridor.
The project's pricipal pay items, such as electrical systems, technology refresh, and traffic management, are lump sum items which means the bidders must pay much greater attention to the breadth and acccuracy of their material takeoffs (including fully vetting the table of quantities provided in the drawings) than would be necessary for unit price items, since the quantity risk for the lump sum items lies with the contractor.
Furthermore, another major Caltrans project similar in nature to this one has been postponed and is now bidding only one week prior to this project's bid date. The amount of estimating/bidding work crammed into such a short period of time is overloading not only our own estimators but those of our subcontractors and suppliers.
Considering all the above, we request that the bid opening date for this project be postponed by three weeks to allow bidders ample time to complete and review their estimates.
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Response #2:The bid open is expected to be delayed at least two weeks. Official notice of bid open delay is provided through addendum only.
Response posted 06/05/2025
Inquiry #53: On Drawing E-5, the vault located at station “EB1” 123+50 lists fiber numbers 77 and 17. According to Drawing E-1 notes and ED-55, this conduit run is identified as the Bundle 3 fiber trunk line, consisting of 2 - 288 SM fiber optic cables, continuing along Route 880 from this vault. However, the electrical plans and cable assignment tables indicate that the Bundle 3 fiber trunk line is routed along Route 80/580 to the Route 80/780 junction, not along Route 880. Please confirm the correct bundle designation and routing of the fiber trunk line along Route 880.
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Response #2:Bundle 3 ends where note 17 is shown on E-5. It is the same method as indicated in note # 77.
Response posted 06/24/2025
Inquiry #54: Electrical Drawing E-106, north of station “FR” 96+50, denotes number 77 to a non-existing conduit run. There seems to be a drawing line missing at this location. Please clarify the intended connection point at this location.
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Inquiry #55: 3. Fiber Optic Network Layout Drawing ED-15 shows the trunk line fiber running from HUB 1 to Vault SV119, the hub located at the office. However, based on the stationing of the laterals on ED-15 and the routing shown in the electrical plans, the fiber appears to terminate at DT408. Please clarify the intended routing from DT408 at station “FL” 36+00 to Vault SV119 at office on 22nd Street Oakland.
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Inquiry #56: DT310, TV106, DT615, and E33V8 are shown on the fiber layout Drawing ED-4 but do not appear on the corresponding electrical plans. Please clarify the status and intended inclusion of DT310, TV106, DT615, and E33V8 on the electrical plans.
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Inquiry #57: On the Fiber Optic Network Layout, CM604 appears twice on Drawing ED-7, and CM606 on Drawing ED-8 is a repeat of CM606 from ED-7. Please provide clarification on the correct labeling and placement of CM604 and CM606.
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Inquiry #58: Upon review of both the Caltrans 2023 Standard Specifications and the Job Special Provisions, we cannot find any Equipment specifications or part numbers for the following:
a. Controller Server
b. Media Converter
c. Aggregate Ethernet Switch
d. Video Server
e. Computer Cabinet
f. FDU Unit
Inquiry submitted 06/04/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/05/2025
Response #2:Please refer to the Caltrans 2024 Standard Specifications and Section 87 Electrical Systems on the Specifications.
Response posted 06/24/2025
Inquiry #59: Section 13 Water Pollution Control states this project's risk level is 3. Please provide Caltrans' preliminary Risk Assessment so we can compare our calculations. We believe this project should be a Linear Underground/Overhead Project (LUP) Type 1 or 2.
Inquiry submitted 06/05/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/06/2025
Inquiry #60: I am trying to square up the cold plane, tack, and asphalt quantities associated with Bid Items 53, 54, and 55.
Summary of Quantities Sheet Q-1 points bidders to sheets C-1 to C-3 for these items.
Sheets C-1 to C-3 list tens of thousands of lineal feet of trenching in pavement.
The asphalt backfill shown on the ED plan sheets show a 4' wide pavement section.
350 SQYD of cold plane makes no sense when considering there are tens of thousands of lineal feet of trenching in pavement travel lanes. It is important to get these quantities as accurate as possible when bidders must also concern themselves with things like the 15% DBE goal.
Please confirm quantities for bit items 53, 54, and 55.
Inquiry submitted 06/06/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/06/2025
Inquiry #61: Drawings EQ-1 calls out 3 EA Edge Ethernet switches, media converters and power supplies. Drawing E-24 has 3 locations that call out note 43 which call out Edge Ethernet switches, media converters and 2 SFP’s and 4 locations that call out note 46 which call out Edge Ethernet switches, media converters and powers supplies. Should the contractor follow EQ-1 table, or the plan view E-24 for the desired quantities?
Inquiry submitted 06/06/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/09/2025
Response #2:Provide hardware for all cabinets. Bid to cover all elements as per plan sheets.
Response posted 06/26/2025
Inquiry #62: Drawing E-24 calls for a new radio cabinet that is not shown on EQ-1. Should the contractor furnish and install the new radio cabinet?
Inquiry submitted 06/06/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/09/2025
Response #2:Furnish and install new radio cabinet.
Response posted 06/24/2025
Inquiry #63: Drawings E-114 and E-115 call for new HUB equipment in the existing racks and new racks. What equipment is required to be furnished and installed by the contractor?
Inquiry submitted 06/06/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/09/2025
Response #2:Entire hardware will be provided by contractor e.g. power supply, edge switch, aggregate switch etc. Refer to ED sheets.
Response posted 06/24/2025
Inquiry #64: Technology refresh drawings E-116 and E-117 call for new CCTV, CMS, and TMS equipment to be furnished and installed inside of existing cabinets. Please provide specifications for the desired equipment, and or the approved equipment for each of the items.
Inquiry submitted 06/06/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/09/2025
Inquiry #65: Drawing ED-2 shows new fiber going into the D4 office. Please provide details on the work that is required at the D4 TMC office.
Inquiry submitted 06/06/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/09/2025
Response #2:This project scope ends on sheet E-113.
Response posted 06/24/2025
Inquiry #66: Can you please post the attendance list from the mandatory Webex meeting that was held on June 2nd? Thank you!
Inquiry submitted 06/09/2025
Response #1:The list has been posted.
Response posted 06/09/2025
Inquiry #67: Sheet E-8 item 77 shows excavation in that area and it's actually hard to determine if its in dirt or on the bike path. More clarity on where exactly the locations of the trench is to excavated. This is on multiple sheets that a contractor has to guess which could cost the contractor to bid it wrong and could be costly.
Inquiry submitted 06/10/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/10/2025
Response #2:The inquiry has been received and submitted for consideration.
Response posted 06/10/2025
Inquiry #68: E-8 calls out 77 which is excavation of trench then it tells you to match line E-98 which calls out to match E-8 and E-7 which calls out 88 attached to structure. This is so confusing, please show where the conduit is to brought up to the structural install.
Inquiry submitted 06/10/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/10/2025
Inquiry #69: Sheets E-116 and E-117 do not clearly depict the quantity or exact locations of the detection loops to be replaced or installed as new as part of the TMS Refresh items.
Example:
Sheet E-117 shows a quantity of one (1) each for “New Detection (Loops)” with the item location noted as "ON-RAMP". The legend also indicates one (1) “Signal Head” at the same “ON-RAMP” location. However, the first TMS location listed on Sheet E-116, TMS ID: DTA41, Location: CLEVELAND AVE OFF-W-DIAG—refers to an off-ramp, which currently operates under stop control and does not have existing signal heads. Furthermore, Sheet U-137 does not show existing loops located on this Off-Ramp.
To ensure accurate takeoffs and bidding, please clarify the following:
• The correct quantity and placement of loop replacements per location
• Whether signal heads and detection loops are actually required at each listed TMS location
• Any discrepancies between the plans and field conditions
Clearer guidance is needed to properly quantify the work required for each Technology Refresh item.
Inquiry submitted 06/11/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/11/2025
Inquiry #70: What is the difference between Bid Item #62 (Miscellaneous Metal) and Bid Item #63 (Miscellaneous Metal (Bridge))?
Both items are shown at EB Carquinez Bridge (Structure 23-0015R).
Inquiry submitted 06/11/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/11/2025
Response #2:Yes, both Item 62 and 63 are only for the Carquinez bridge. Item 62 is for the fiber optic support brackets on the bridge. Item 63 is for the CCTV bridge mounts and access platforms. The brackets are spaced every 30’.
Response posted 06/26/2025
Inquiry #71: On C-1 (Sheet 14), the conduit quantity chart indicates 275’ of conduit to be installed on structure on Sheet E-11. While Note 2 on Sheet E-11 reflects this same length, it does not specifically state that the conduit is to be installed on structure, nor does it reference any applicable structural details. Notes 2, 11, 13, 19, and others alike leave the installation method open for interpretation.
Please clarify which conduits are to be installed on structures by revising the open for interpretation notes shown on the Electrical sheets that are being referenced in charts on C-1 through C-3 by specifically stating the installation methods.
Inquiry submitted 06/12/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/12/2025
Inquiry #72: Drawing E-40 calls out Note 49 INSTALL NEW RWL CABINET (Radio Cabinet). Drawing ED-25 shows the circuit breaker addition for a new HUB cabinet. Please confirm if the new cabinet on E-40 is a new radio cabinet, or a new hub cabinet to be furnished and installed by the contractor.
Inquiry submitted 06/13/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/13/2025
Inquiry #73: Drawing E-93 calls out Note 66 INSTALL NEW RADIO CABINET. Drawing ED-26 shows the circuit breaker addition for a new HUB cabinet. Please confirm if the new cabinet on E-96 is a new radio cabinet, or a new hub cabinet to be furnished and installed by the contractor.
Inquiry submitted 06/13/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/13/2025
Response #2:A new radio cabinet is to be installed.
Response posted 06/17/2025
Inquiry #74: If the contractor is to provide and install the new radio cabinets, please provide bill of material for the new radio cabinets.
Inquiry submitted 06/13/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/13/2025
Response #2:Contractor will procure the material.
Response posted 06/26/2025
Inquiry #75: Will there be another opportunity to attend the Prebid meeting? Is there a prebid mandatory for subs as well?
Inquiry submitted 06/16/2025
Response #1:There is only 1 Pre-Bid Meeting. There is no dedicated pre-bid meeting for subs. Subs can participate in the project without attending the mandatory pre-bid meeting.
Response posted 06/16/2025
Inquiry #76: The Multi Duct Conduit System 80/580 El Cerrito Separation General Plan Detail A shows (1) 5" Conduit (Type 1) with a Fabric 4-Cell Sleeve Innerduct to be installed below the concrete barrier on the side of the bridge . On both the North and South ends of this bridge conduit installation, Plan Sheet E-27 (South End) and Plan Sheet E-28 (North End), Note 77 is shown, which is "4 - 1 1/2" C, 2 - 288 SM FO Cables, See Details on Sheet ED-23 and ED-55." How is the 5" bridge conduit and fabric 4-Cell Sleeve Innerduct to transition to 4 - 1 1/2" Conduits on each end? Please provide a detail.
Inquiry submitted 06/16/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/16/2025
Inquiry #77: The Multi Duct Conduit System Cerrito Creek General Plan Detail A shows (1) 5" Conduit (Type 1) with a Fabric 4-Cell Sleeve Innerduct and (1) 8" PVC Pipe for Future MMBN to be installed in a slurry cement backfilled trench. On both the North and South ends of this conduit installation, Plan Sheet E-30 (North and South Ends), Note 77 is shown, which is "4 - 1 1/2" C, 2 - 288 SM FO Cables, See Details on Sheet ED-23 and ED-55." How is the 5" Conduit with a Fabric 4-Cell Sleeve Innerduct to transition to 4 - 1 1/2" Conduits on each end? Also, are we to cap both ends of the 8" PVC Pipe for Future MMBN? Please provide a detail.
Inquiry submitted 06/16/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/16/2025
Inquiry #78: Conflicts exist between the Electrical Plans and Structural Details regarding the conduit installation methods at several locations. The Electrical Sheets shown below reference underground trenching installation notes, while the corresponding Structural Plans indicate conduit is to be installed on structure. Installation of conduit on structure would mitigate open trenching across roadways, wetlands, and railroads. Please confirm the required method of installation at the following locations, and revise the plan sheets accordingly:
• Sheets E-27 to E-28 from, “EB2” Line STA 381+42 to STA 396+27: Trenching Note 77 vs. Structural Sheets 474–476 (Conduit on Structure)
• Sheet E-69, from “AM4” Line STA 931+85 to STA 940+24: Trenching Note 77 vs. Structural Sheets 485–488 (Conduit on Structure)
• Sheet E-105, from “NW” Line STA 80+20 to STA 81+43 & STA 82+58 to 83+80: Trenching Note 85 vs. Structural Sheets 568–571 (Conduit on Structure)
• Sheets E-105 to E-106, from “FR” Line STA 110+41 to STA 100+33: Trenching Note 85 vs. Structural Sheets 572–576 (Conduit on Structure)
• Sheet E-106 to E-107, from “FL” Line STA 96+25 to STA 86: Trenching Note 85 vs. Structural Sheets 577–580 (Conduit on Structure)
• Sheets E-110 to E-111, from “FL” Line STA 49+16 to STA 35+51: Trenching Note 85 vs. Structural Sheets 581–587 (Conduit on Structure)
Inquiry submitted 06/16/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/16/2025
Inquiry #79: On Plan Sheet E-57, the proposed conduit path routed across the Mainline is shown being directionally bored to a new pull box shown in the middle of the westbound Mainline. The conduit then ties into a controller cabinet located on the overcrossing. This is not constructible. Contractor recommends revising plan sheet to install conduit on Richmond Parkway structure from “EB4” Line - STA 775+6 to STA 776+84. If the conduit is to be installed on structure, provide the applicable structural details. Please review and confirm conduit installation method.
Inquiry submitted 06/16/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/16/2025
Inquiry #80: On Plan Sheets E-70, the conduit installation method for the Highway 4 crossing is shown as trenching (per Note 77), which is not constructible. Contractor recommends revising plan sheet to install conduit on structure from “AM4” Line STA 249+28 to STA 953+71. If the conduit is to be installed on structure, provide the applicable structural details. Please review and confirm conduit installation method.
Inquiry submitted 06/16/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/16/2025
Inquiry #81: The Multi Duct Conduit System Details for the Carquinez Bridge (Both Eastbound and Westbound Bridges) show (1) 5" Conduit (Type 1) with a Fabric 4-Cell Sleeve Innerduct. Sheets E-84 through E-89, Notes 32 (Westbound Bridge) and 76 (Eastbound Bridge) describe a 4" C, Containing 4 - 1 1/4" Innerduct (Conduits Inside Casing). Are we to install (1) 5 Conduit (Type 1) with Fabric 4-Cell Innerduct or (1) 4" conduit with (4) 1-1/4" Innerducts on the Eastbound and Westbound Carquinez Bridges?
Inquiry submitted 06/17/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/17/2025
Inquiry #82: Can two subcontractors be listed for the same or similar type of work on the same bid item number? Can two subcontractors be listed for the same or similar type of work on different bid line items?
Inquiry submitted 06/18/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/18/2025
Response #2:Yes. Two subcontractors can be listed for the same or similar type of work on the same bid item number. Two subcontractors can be listed for the same or similar type of work on different bid line items.
Please be aware that the total percentage on each item must not be over 100% of the listed work. For example, two subs listed for the same bid item at 50% each, is fine; Two bidders at 100% each is grounds for the Prime to self-perform the work.
Response posted 06/25/2025
Inquiry #83: Can the prime contractor list multiple directional drilling subcontractors on the same bid item?
Inquiry submitted 06/18/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/19/2025
Response #2:Please refer to bidder inquiry #82.
Response posted 06/26/2025
Inquiry #84: Does the subcontractor (1st tier sub) need to provide the name of the traffic control contractor (2nd tier sub) at the time of bid submission by the prime?
Inquiry submitted 06/23/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/24/2025
Inquiry #85: Can you please provide an icon legend for the Modify Existing Electrical layout sheets that clearly defines the icons used for vaults, boxes, cabinets, etc. and that can clarify which are intended as existing or to be installed.
Inquiry submitted 06/24/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/25/2025
Inquiry #86: On Sheet E-24om the west side of 80/580, the layouts indicate a trenching alignment cutting across brand new round-about features that could easily be drilled without the need for elaborate and expensive restoration. The layout also shows some existing cabinets and boxes standing in the middle of new roadways and sidewalks. It appears as if the improvement lines conform to conditions that existed before the round-abouts were constructed - please review and clarify rather or not we are to cut through the round-abouts, new walk, and new pave in order to construct this location.
Inquiry submitted 06/24/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/25/2025
Inquiry #87: Fiber Optic Vaults (Type 2, Type 3, and Type 4) are shown on Plan Sheets ED-46, ED-47, and ED-48. Are these vaults to be used anywhere on this project? It appears that the only Fiber Optic Vaults used on this project are on ED-40 and ED-41. Please confirm.
Inquiry submitted 06/25/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/25/2025
Inquiry #88: On Sheet E-8 shows a conduit run to be excavated (77) then refers to sheet E-98 which shows on the conduit run on the structure. Please identify where the conduit run is to attach to the structure.
Inquiry submitted 06/27/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/27/2025
Inquiry #89: On Sheet E-114, Note 72 is referenced, which states, "Install hub equipment in existing B cabinets, see Sheet ED-36 for detail." Sheet ED-36 shows a hub cabinet foundation, but it does not show any hub equipment details. What hub equipment are we to install per Note 72 on Sheet E-114?
Inquiry submitted 06/30/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/30/2025
Inquiry #90: Please provide a detailed drawing for Note 70 on sheet E-2, which describes a 24 inch rackmountable 42U tall cabinet.
Inquiry submitted 06/30/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 06/30/2025
Inquiry #91: Please confirm if 8" Welded Steel Pipe casing is intended for all horizontal directional drill crossings as is show on ED-56 (Sheet 462).
Inquiry submitted 07/01/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 07/01/2025
Inquiry #92: E-39 & E-40 shows a distance of approximately 77' of structural conduit crossing over both the Ohio St OH & 47th St PUC. However, when comparing to google earth the total distance is roughly 386'. Please revise the E sheets to accurately reflect the total distance of conduit on structure.
Inquiry submitted 07/02/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 07/02/2025
Inquiry #93: Are the structures shown on structures pages (sheets 474 - 587) the only structures which contractors are expected to mount the conduit?
Inquiry submitted 07/03/2025
Response #1:The inquiry has been received and submitted for consideration.
Response posted 07/03/2025
Inquiry #94: Given the large number of bidder inquiries still to be answered (approx. half of them) we request that the bid date be postponed at least 2 weeks to allow bidders adequate time to process the responses, when they come, and incorporate them into their bids.
Inquiry submitted 07/03/2025
Response #1:The Bid Open will be postponed by one week. Official notice of Bid Open is only provided through Addendum.
Response posted 07/03/2025
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.